WWTP


With the heavy rains, the Waste Water Treatment Plant had some issues.  Both EPA and DEP have signed off on the temporary corrective measures.

town seal

TOWN OF MEDFIELD

MASSACHUSETTS

“Department of Public Works

 

MAURICE G. GOULET

Director of Public Works

55 North Meadows Road

Medfield, MA 02052

(508)359-8597

Fax (508) 359-4050

 

TO:            Board of Selectmen

Michael Sullivan, Town Administrator

Kristine Trierweiler, Assistant Town Administrator

Water and Sewer Board

 

FROM:    Maurice G. Goulet. Director of Public Works

MEMORANDUM

 

 

 

DATE:            April 4, 2017

SUBJECT:      WWTP Issue

We experienced an influx of water at the Wastewater Treatment Plant due to excessive rains. This influx of water forced us to bypass partial treatment areas at the plant. The UV Control System at the end of the treatment areas is in need of repair. A temporary chlorine tank and feed has been set up at the final stage of treatment for disinfection. This chlorine tank is necessary for the interim until the UV Control System can be repaired and put back on-line. New controls and repair parts have been ordered and will be installed as soon as possible. When the UV Control System is running properly, the chlorine tank and feed will be removed.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s