MSH watertower filled


water towers at MSH

Photo by Richard DeSorgher

 

FYI. Update on hospital water tower. Mike S

 

———- Forwarded message ———-
From: Paul C. Millett
Date: Fri, Jul 1, 2016 at 1:29 PM
Subject: Hospital Road Tank Status and DEP Communication
To:
Ken, Mike and Jeremy:

 

Tank filling started last week (Friday June 24) and it took almost a full week to fill the tank, due to high water demand in the system, warm weather and lack of rain.

 

I spoke with Dave O’Toole. I also left a message for Paula Caron at MADEP-Central Region.

I stated that the new tank is nearly complete, and that samples were taken this morning.

I also offered to meet her or any other DEP representative on site if necessary, and asked for a return call today or on Tuesday.

 

We will have the lab results back on Tuesday July 5.

 

The altitude valve was adjusted on Tuesday by the field representative.  The electric service and meter have been energized. The SCADA work is scheduled for Tuesday.

 

Fencing will happen after the paving work around the outside of the tank. We will get a schedule from Oliveira construction for the paving.

 

We will generate a punch list next week.

 

Overall, I am hoping that the tank will be ready to be placed in service by next Friday July 8 and be deemed substantially complete.

 

Thereafter, the existing tank demolition can be scheduled.

 

Regards,

 

Paul

 

Paul C. Millett, P.E.

Project Manager

 

Environmental Partners Group, Inc.,

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s